EXPLORATION
AND DEVELOPMENT OF THE SEPON GOLD AND COPPER DEPOSITS, LAOS.
Tony
Manini and Peter Albert,
Oxiana Limited, Level 9, 31
Queen Street, Melbourne, Victoria 3000.
Key
Words: copper, exploration, feasibility study, gold, Laos, mine
Introduction
The Sepon project comprises
a 1947 square kilometre contract area located approximately 40 kilometers north
of the town of Sepon, in Savannakhet province of south-central Laos (Figure 1).
Gold and copper deposits
discovered in the Sepon district by CRA/RioTinto (1993-1999) and Oxiana
(2000-2003) contain over four million ounces of gold and 1.2 million tonnes of
contained copper. Seven gold and one copper deposit occur in separate adjacent
deposits over five kilometers.
Gold
mineralisation occurs as fine disseminations in highly altered calcareous
sedimentary rocks with many affinities to the Carlin style gold deposits of
Nevada, USA. The Khanong copper deposit is a near surface high grade supergene
chalcocite and oxide copper body derived from the weathering of a replacement
style massive sulphide deposit developed in shallow dipping, highly sheared
carbonate rocks.
Oxiana acquired an 80% stake
in the project in early 2000 with the vendor Rio Tinto retaining a 20%
shareholding. Upon finalisation of the asset sale in August 2000 Oxiana
immediately commenced feasibility and environmental - social impact studies for
a two stage development of the Sepon gold and copper projects.
Following a 12 months
construction period, the 1.25 mtpa Sepon gold mine poured first gold in late
December 2002 and has now been operating successfully for more than nine
months. Extensive exploration and development drilling in 2003 has
significantly upgraded the gold resource and reserve base to 14.2Mt @ 3.43g/t
Au (70% increase in reserve ounces) and a study to expand the gold project has
been initiated.
Copper Project feasibility
and environmental - social impact studies were completed over 10 months in 2002
including pilot plant test work at Lakefield Research in Canada. The project is
designed to produce 60,000 tpa of LME grade copper cathode.
In January 2003 engineering
and construction of the Copper Project was awarded to a joint venture between
Bateman Limited and Ausenco Limited and after 9 months of a 27 months program
the project is on schedule to produce first copper in March 2005.
New discoveries continue to
be made and exploration for both gold and copper is
ongoing with many targets remaining to be assessed. Aggressive year
round drilling campaigns continue to expand both the resource and reserve bases
and test the pipeline of new gold and copper targets being generated.
Oxiana is focused on
maximizing its investment in the Sepon project through continuous exploration
and incremental expansion of its gold and copper mining operations over time.
The ultimate production potential of the Sepon District is considered to be
significantly greater than its current scale.
Figure 1. Location of the Sepon Project
Project History
Although numerous river
valleys of the Sepon district have long been the subject of sporadic artisanal
gold panning, no assessment of the hard rock potential had ever been undertaken
prior to the involvement of CRA Exploration in 1990.
Potential of the Sepon
district was first recognised by CRA geologists during follow up of UNDP
(United Nations Development Program) mineral occurrence data and information
sourced from archives in the Laos Department of Geology and Mines. While the
style of mineralisation was not immediately discernable, the association of
porphyry intrusives, district scale alteration and extensive gold occurrences
(alluvial and hardrock) was considered highly significant. When the assay
results for 18 rock samples reported between 3.6 and 55.9g/tAu prospectivity
was confirmed.
An application covering 5000
square kilometers in Savannakhet and Khammouane Provinces was submitted to the
Lao Government in early 1991. Following two years of pioneering negotiations, a
Mineral Exploration and Production Agreement (MEPA) similar to the Indonesian
Contract of Work was signed in September 1993. This Agreement provides for the
exclusive right to explore, mine, process, transport and market all minerals
from the MEPA area and clearly defines the life of project commercial and fiscal
framework.
Intensive exploration by
CRA/RioTinto between 1993 and 1999 resulted in the discovery of around 3 Moz of
gold and an estimated 0.9 Mt of contained copper in six separate deposits.
In 1999 Rio Tinto decided to
divest of the Sepon Project because it did not satisfy the companies resource
size criteria. The project was put to competitive tender and following
extensive due diligence Oxiana successfully bid for an 80% stake in the project
in early 2000. Rio Tinto retained a 20% shareholding and has continued to
provide strong support for Oxiana’s subsequent gold and copper mine
developments.
Exploration
and Resource Evaluation
Regional exploration of the
broader Sepon area commenced in late 1994 following the discovery and initial
assessment of the Discovery and Namkok deposits. Programs comprising detailed
regional stream sediment and rock geochemistry, geological mapping, airborne
magnetic and radiometric surveys and remote sensed Landsat and photo
interpretation were completed over the entire 5000 square kilometer area in
late 1994 and 1995.
Airborne
magnetics proved useful in regional structural analysis but was of limited use
in direct targeting. Although the porphyry bodies do not have discernable
magnetic signatures, surrounding skarns are detectable. Radiometrics clearly
mapped potassic alteration of the porphyry bodies, including dykes and sills,
where exposed.
Stream sediment geochemistry
(-80#) clearly outlined a standout high order district scale multi-element
geochemical signature over 400 square kilometers around the initial
discoveries. Subsequently, this highly mineralised trend representing the Sepon
Mineral District has been the dominant focus of exploration for gold and
copper.
While exploration at the
district scale has utilised a wide spectrum of techniques and technologies,
programs have always maintained a strong geological focus with an emphasis on
basic prospecting, geological mapping and drilling.
High quality geological,
geochemical and geophysical data has been systematically collected,
progressively compiled, interpreted and revised to develop a solid
understanding of the geology, tectonic framework, and mineralisation at
regional, district and prospect scales.
Detailed
exploration has incorporated geological mapping ranging in scale from 1:25000
to 1:500, soil and rock geochemistry and ground geophysics including IP, CSAMT,
magnetics, radiometrics and gravity. Soil geochemistry on 400 meter spaced lines has been completed over the entire
400sqkm district along with extensive rock geochemistry.
Extensive use of oriented
diamond core drilling early in the project life and the utilisation of a wide
spectrum of specialist consultants to compliment the field skills of the
project exploration team provided a solid basis for understanding the complex
interrelationships between mineralisation, stratigraphy, structure and
intrusive phases.
As part of the project
feasibility studies, a detailed drilling program comprising approximately 900
holes and 30,000 meters was completed in 2000-2002 to evaluate the oxide and
partial oxide components of the gold deposits, and the supergene copper
deposit.
The rapid transition from
exploration to resource evaluation and feasibility required specialist input as
no member of the exploration team had prior resource evaluation experience.
Resource consultants Hellman and Schofield Pty Ltd who had conducted the
resource due diligence for Oxiana’s acquisition of the Sepon project were
contracted to develop and assist implementation of appropriate drilling,
logging, sampling, assaying and quality control – quality assurance protocols
and to upgrade database systems.
Drilling utilising two RC
rigs was completed on a nominal 50 metre drill pattern with priority areas for
early mine development infilled to a 25x25 metre pattern. Diamond core drilling
was used to collect sample for metallurgical test work and to twin several RC
holes in each deposit.
Geostatistical resource
estimates were completed by Hellman and Schofield Pty Ltd using the multiple
indicator kriging (“MIK”) method for gold and ordinary kriging for copper.
New discoveries continue to
be made and exploration for both gold and copper is
ongoing with many targets remaining to be assessed throughout the
district. Development drilling and exploration by Oxiana in the first half of
2003 has discovered two new gold deposits and expanded the gold resource from
3.5 to 4.2Moz (before depletion). An additional discovery of high grade gold
mineralisation approximately 20 kilometers west of the process plant will be
assessed immediately following the current 2003 wet season
Since the commencement of
mining, detailed pit mapping and analysis of grade control drilling data has
been utilised to significantly upgrade geological understanding of the
deposits, in particular the controls on mineralisation. This enhanced
geological framework is being coupled with existing data sets to enhance the
predictive capacity of exploration targeting.
Aggressive drilling
campaigns utilising three RC and two diamond core rigs are continuing to expand
the resource base and test a pipeline of gold and copper targets being
generated.
Geology
and Mineralisation of the Sepon District
Sepon Mineral District
stratigraphy comprises Devonian to Carboniferous aged continental fluvial and
shallow to deep marine sediments deposited in a half graben basin. The
sedimentary package has been divided into nine lithology based formations
(Morris 1995) of which the lower and upper contacts of formation 6, a
calcareous, carbonaceous mudstone host most of the known gold mineralisation.
Sediments generally dip
moderately towards the north and north-west. Dominant fault directions are
north-west parallel to the Truongson fault system and east-west parallel to the
basin bounding faults. The intersection of east-west and north-east trending
faults are important in localising mineralisation and rhyodacite porphyry
intrusive stocks and associated dyke and sill complexes of similar composition.
Four broad
alteration/mineralisation styles are recognised namely quartz stockwork
porphyry Mo, Cu-Au skarn, Cu-Au carbonate replacement, and sediment-hosted Au.
Gold mineralisation is
localised in structural and stratigraphic fluid traps which have many
affinities with the sediment-hosted gold deposits of the Carlin Trend, Nevada,
USA. Mineralisation is finely disseminated and closely associated with
decalcification and variable silica replacement of calcareous rocks along
structures and at lithological contacts. Geometry of the gold ore is controlled
by anticlinal structures and shallow dipping stratigraphy, structure and
porphyry sills. Residual deflation surface remnants of the primary
mineralisation are also recognised.
Copper mineralisation covers
a variety of primary and secondary styles. Along the contacts of the intrusive
stocks, Cu-Au skarns are developed, while outbound of the skarn front lower
temperature silica-sulphide replacement of carbonate rocks is common.
Weathering and mobilization of the primary mineralisation gives rise to a number
of secondary ore types. The Khanong copper deposit is a near surface high grade
supergene derived chalcocite and oxide copper resource derived from weathering
of a replacement style semi massive sulphide body hosted by shallow dipping,
highly sheared carbonate rocks.
In-situ supergene enrichment
of this sulphide protore resulted in the development of a clay hosted, high
grade chalcocite enrichment blanket immediately beneath which lies a very high
grade copper oxide zone comprising malachite ± azurite ± cuprite ± minor native copper (Loader
1999).
A schematic model showing
the broad spectrum of mineralisation styles represented in the Sepon Mineral
District is shown in figure 2.
Figure 2. Schematic model of
mineralisation styles in the Sepon Mineral District (after Sillitoe 1990)
Project
Development
Background
Following the completion of
all legal and approval documentation for the Sepon project acquisition in
August 2000, development of the project commenced in earnest. Early in the
project development phase Oxiana decided that the most pragmatic approach was
to develop the project in two stages, the smaller gold project first and the
much larger copper project later. The major advantages of this approach included
reduced front end project funding requirements, lesser early stage technical
risk, and the early demonstration of a mining project’s viability in an
untested host country .The following timetable indicates the broad activities
that have taken place since August 2000.
August 2000 |
Commencement of Gold FS
and Gold ESIA. |
September 2001 |
Completion of Gold FS and
ESIA. |
November 2001 |
Commencement of Copper FS
and Copper ESIA. |
December 2001 |
Commitment to Gold Project
development. |
October 2002 |
Completion of Copper FS
and Copper ESIA. |
December 2002 |
First gold poured at
Sepon. |
January 2003 |
Commitment to Copper
Project Development. |
March 2005 |
Scheduled first production
of Copper at Sepon. |
Gold Project Feasibility
Study (FS) and Environmental and Social Impact Assessment (ESIA)
In August 2000 Oxiana was a
small company with a market capitalization less than AUD30M and few employees.
Oxiana elected to manage the FS and ESIA in-house and to utilize best available
consultants. In this way Oxiana maintained a hands on approach and was able to
provide appropriate direction, while at the same time being assured of having
skilled resources available at short notice. At the time, the Chatree Gold Mine
in Thailand had just completed a FS and Oxiana sought to gain some synergies by
utilizing consultants from that project. Key consultants included:
Geology and Resources |
Oxiana and Hellmann &
Schofield |
Mining |
AMDAD |
Metallurgy |
P. Lewis & Associates |
Engineering |
Bateman Limited. |
Geotechnical |
Golders. |
Environmental & Social |
NSR Consultants and Earth
Systems Lao |
A considerable amount of
drilling and resource evaluation as well as metallurgical test work was
required and therefore in reality the FS was both a pre- feasibility study and
a feasibility study.
Oxiana understood that
project financing requirements would entail an array of international
stakeholders all of whose agendas would need to be fulfilled. A particularly
important party was the International Finance Corporation (IFC) who played a
significant role in setting the terms of reference for the ESIA. This
inevitably added time and cost to the study phase, however the standard of
documentation as well as the IFC’s direct involvement have had downstream
benefits for the project and the company’s dealings with other stakeholders.
Oxiana have continued to adopt the IFC (World Bank) standards during gold
operations and for the copper ESIA.
Although the FS and ESIA
passed all IFC requirements Oxiana was ultimately able to fund the US$45M cost
of the gold project from equity.
Limited funds and a desire
to advance the project as rapidly as possible dictated that only sufficient
resources and reserves to demonstrate the Project’s economic viability were
proved up. It was clearly understood and expected that the resources and
ultimately reserves would be much greater than those developed during the FS.
Gold Project Execution and
Current Status
Oxiana awarded the
engineering and construction of the Gold Project to Ausenco Limited who had
successfully completed the Chatree Gold Mine in Thailand and were also
perceived to have a strength in developing small–medium sized gold mines in
remote environments.
The development of the Sepon
Project had a number of challenging aspects namely a significant wet season for
4 months of the year, no access to power and no telecommunication facilities,
very poor site access by a dirt road which was often cut off during the wet
season and unexploded ordnance across the project site – a remnant of the
Vietnam war.
Nonetheless the Project
produced first gold on schedule in December 2002 and has been operating
successfully for more than 9 months. A study to expand the gold project has
recently been initiated following a significant upgrade of the resources and
reserves (70% increase in reserve ounces).
A key success factor in the
ramp up of the Project was the recruitment of the senior team. All recruitment
was undertaken in-house, typically targeting individuals who along with the
requisite technical skills also needed to have had offshore experience
preferably in Asia on a fly-in-fly-out roster; demonstrated high achievement
and commitment levels; and most importantly a high level of cultural
sensitivity and understanding.
Copper Feasibility Study and
Environmental and Social Impact Assessment
The Copper FS and ESIA were
undertaken in a similar fashion to the gold studies, although the technical
complexity was much greater. As such Oxiana applied increased resources to this
aspect of the work and the engineering company was given a greater over-arching
management role. The team comprised:
Management |
Bateman and Oxiana. |
Geology and Resources |
Oxiana, Hackman &
Associates, Hellman & Schofield. |
Mining |
AMDAD. |
Metallurgy |
Bateman, Oxiana, David
Dreisinger. |
Engineering |
Bateman / Knight Piesold. |
Environmental & Social |
NSR Consultants and Earth
Systems Lao. |
These Studies took 10 months
to complete which included a pilot plant facility at Lakefield Research in
Canada. The process flowsheet comprises crushing and grinding, atmospheric
leach, solid-liquid separation, flotation and pressure leaching. This elegant
flowsheet is anticipated to yield in excess of 90% copper recoveries and
produce 60,000 tpa of LME grade copper cathode.
Copper Project Current Status
In January 2003 engineering
and construction of the copper project was awarded to a joint venture between
Bateman Limited and Ausenco Limited. After 9 months of a 27 months program the
project is on schedule to produce first copper in March 2005. Engineering is
+30% complete, site bulk earthworks are +70% complete and concrete construction
has commenced.
Project Financing
Financing is outside the
scope of this paper, however the financing arrangements and strategy have had a
significant influence on the execution of both Projects.
Sovereign and political
risk, especially from the financial community has always been a major focus
with the Lao PDR perceived as a communist country with little significant
foreign investment track record and no mining infrastructure. Oxiana believed
that this issue had the potential to significantly delay the Project and in the
latter half of 2001 successfully moved to fund the Gold Project entirely from
equity.
Following successful
development of the Gold Project potential investors have been much more willing
to consider investing in Laos and Oxiana is close to finalising the debt
financing package for the Copper Project with a consortium of European
commercial banks, development banks and credit agencies. Adoption of World Bank
Guidelines for social and environmental criteria at an early stage in the
Project’s development has been significant in securing the debt funding
package.
Government
and Community Relations
As discussed earlier, the
Sepon Project is a “flagship” foreign investment enterprise for Laos. The Sepon
MEPA has been successfully used for over 10 years to achieve the successful
implementation of the Project and both parties have abided by the content and
intent of the Agreement without exception.
The Government of Laos is
very open and encouraging of foreign investment and all potential investors who
have visited Laos have been impressed by the support given to the Project by
the Government. Oxiana endeavors to ensure that all four levels of Government
in Laos; Central, Provincial, District and Village are kept informed at all
times and have the opportunity to participate in the development of this Lao
Project.
In any context, potentially
the most important aspect of a successful project is an open, trusting and
sharing relationship with the local community. Oxiana’s philosophy is that our
ultimate mandate to operate lies with the local community and as such Community
Relations takes on a primary role.
Besides job creation and
impacts on the environment, projects in developing countries also have major
impact on social structure, wealth generation and distribution, gender issues,
education, health, capacity building, local area and country development.
Any project in an
environment such as Sepon assumes a large responsibility, not just for the
short term of the mine life, but also for the longer term sustainability of the
area or region in which it operates.
Lessons Learnt
From a project development
perspective a comprehension list of lessons learnt would fill many pages. Key
lessons include:
References
Gregory, C.J. 1991 Sepon Gold Prospect , Laos. CRA internal memorandum report.
Loader, S.E. 1999 Supergene enrichment of the Khanong Copper
Resource, Sepon Project, Lao P.D.R.. Proceedings
PACRIM’99 pp 263-272.
Morris, D.G. 1997 Sepon Project, Laos: Relationships between
precious and base metal mineralization and stratigraphy, diagenetic alteration
and hydrocarbon generation. Rio Tinto
internal report
Sillitoe, R.H. and Bonham,
Jr. 1990 Sediment-hosted gold deposits: Distal products of
magmatic-hydrothermal systems. CRA
internal report
The Feedjit SMEDG Visitor Map
Which one of the red squares is you?